Skip to content
PIS logoIntegrated protection professionally delivered

Resistance passed. Conductor duty did not.

The resistance target passed. The conductor duty did not.

10th of RamadanIndustrial3 min read
A low resistance is only one acceptance checkEngineered approach for PIS-CS-017. Review prospective current and clearing time for every critical path. Check conductor and connection withstand against that duty. Repair damage; verify continuity and the governing calculation. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 017A low resistance is only one acceptance checkENGINEERED APPROACHFAULTED LOADR PASSEDEARTH TESTEREPCCURRENT + TIMEWITHSTAND CHECKResistance and fault-current withstand are independent acceptance checks.1231Review prospective currentand clearing time for everycritical path.2Check conductor andconnection withstand againstthat duty.3Repair damage; verifycontinuity and the governingcalculation.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Engineering concept / vector field note

01

The field problem

Industrial Complex — 10th of Ramadan

Several earthing systems achieved resistance values better than their specified targets, yet abnormal behaviour appeared later.

why the obvious answer can be misleading

Review showed that the conductor network’s fault-current/thermal duty was lower than the prospective duty expected at the installation. Earth resistance alone therefore did not prove that the network could survive a fault event.

02

Why it failed

Review showed that the conductor network’s fault-current/thermal duty was lower than the prospective duty expected at the installation.

Earth resistance alone therefore did not prove that the network could survive a fault event.

03

Follow the engineering

Switch between the field condition and the engineering concept. Trace the path and examine what changes.

Inspect the engineering detail

A low resistance is only one acceptance checkEngineered approach for PIS-CS-017. Review prospective current and clearing time for every critical path. Check conductor and connection withstand against that duty. Repair damage; verify continuity and the governing calculation. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 017A low resistance is only one acceptance checkENGINEERED APPROACHFAULTED LOADR PASSEDEARTH TESTEREPCCURRENT + TIMEWITHSTAND CHECKResistance and fault-current withstand are independent acceptance checks.1231Review prospective currentand clearing time for everycritical path.2Check conductor andconnection withstand againstthat duty.3Repair damage; verifycontinuity and the governingcalculation.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Case 017 · Engineered approach

100%
A low resistance is only one acceptance checkEngineered approach for PIS-CS-017. Review prospective current and clearing time for every critical path. Check conductor and connection withstand against that duty. Repair damage; verify continuity and the governing calculation. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 017A low resistance is only one acceptance checkENGINEERED APPROACHFAULTED LOADR PASSEDEARTH TESTEREPCCURRENT + TIMEWITHSTAND CHECKResistance and fault-current withstand are independent acceptance checks.1231Review prospective currentand clearing time for everycritical path.2Check conductor andconnection withstand againstthat duty.3Repair damage; verifycontinuity and the governingcalculation.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Scroll to inspect. Numbered details match the notes below the drawing. Conceptual geometry; use the case text for the engineering requirements.

What changes

Check conductor cross-section and connections against prospective fault current and clearing time, not only the final resistance target.

Teaching schematic · not to scale© PIS Engineering Academy · All rights reserved
04

Correction & verification

Check conductor cross-section and connections against prospective fault current and clearing time, not only the final resistance target.

Locate and repair any damaged high-current path.

Verification recorded in the case

  • Perform continuity and low-resistance checks after repair and verify the thermal/fault-duty calculation.
  • Record as-built topology and connection points.
  • Repeat the measurement or functional test under a defined condition.
  • Confirm continuity and mechanical integrity of the corrected path.
  • Document instrument/setup, environmental condition and test method.
  • Close the NCR/case only when evidence supports the conclusion.
References & project context

References are reproduced from the PIS casebook. Select the governing edition and project acceptance criteria before using them for a design. The diagrams explain the concept, rather than define construction dimensions.

IEC 60364-5-54; applicable substation/fault-current design requirements.

PIS reviewed field handbook · PIS-CS-017

View the original social card
05

The engineering lesson

An earthing system must both dissipate voltage and survive the current that creates it.

Take the lesson into your next design review.

Keep exploring

Connected lessons.

All cases
Independent drawings, interconnected real equipmentEngineered approach for PIS-CS-008. Create an intentional equipotential architecture. Size and coordinate the common bonding path for its actual duty. Verify continuity, potential differences and functional requirements. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 008Independent drawings, interconnected real equipmentENGINEERED APPROACHPOWERLIGHTNINGICTINTENTIONAL EQUIPOTENTIAL ARCHITECTUREVerify the coordinated network and its functional requirements.1231Create an intentionalequipotential architecture.2Size and coordinate thecommon bonding path for itsactual duty.3Verify continuity, potentialdifferences and functionalrequirements.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
08

Earthing & bonding

Separate earths. Different potentials.

Separate earths created separate potentials.

New Administrative Capital3 min
Metallic protective return versus a soil-only pathEngineered approach for PIS-CS-010. Provide a continuous engineered metallic protective conductor. Coordinate the path with source earthing and the protection scheme. Verify continuity and automatic-disconnection conditions. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 010Metallic protective return versus a soil-only pathENGINEERED APPROACHSTART POINT / PEREMOTE EARTHING BARCONTINUOUS METALLIC PEVerify continuity and the actual automatic-disconnection conditions.1231Provide a continuousengineered metallicprotective conductor.2Coordinate the path withsource earthing and theprotection scheme.3Verify continuity andautomatic-disconnectionconditions.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
10

Earthing & bonding

Soil cannot replace a protective conductor

Soil is not a substitute for a designed protective conductor.

Sheikh Zayed3 min
Foundation ring and natural structural down pathsEngineered approach for PIS-CS-013. Coordinate a closed foundation ring or engineered mesh. Connect and verify the reinforcement used as natural conductors. Inspect and test defined points before concrete conceals them. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 013Foundation ring and natural structural down pathsENGINEERED APPROACHFOUNDATION PLAN + REINFORCEMENT CONTINUITYClosed ring / mesh connected to verified structural paths.1231Coordinate a closedfoundation ring or engineeredmesh.2Connect and verify thereinforcement used as naturalconductors.3Inspect and test definedpoints before concreteconceals them.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
13

Earthing & bonding

A foundation earth is a network

A foundation earth is a network, not a straight line on one side of the building.

New Alamein3 min