Skip to content
PIS logoIntegrated protection professionally delivered
PIS-CS-006/Measurement

Solar earthing & tracker control

One test method cannot describe every part of a solar plant.

Benban, AswanEnergy3 min read
Solar trackers, geology and the measurement objectiveEngineered approach for PIS-CS-006. Profile soil depth and select electrode arrangements from evidence. Use the test method appropriate to isolated or interconnected topology. Verify tracker bonding and correlate measurements with control behaviour. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 006Solar trackers, geology and the measurement objectiveENGINEERED APPROACHTRACKERARRAY STRUCTURE / TRACKER DRIVE / CONTROL INTERFACESSoil model, test topology and control behaviour are separate checks.1231Profile soil depth and selectelectrode arrangements fromevidence.2Use the test methodappropriate to isolated orinterconnected topology.3Verify tracker bonding andcorrelate measurements withcontrol behaviour.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Engineering concept / vector field note

01

The field problem

Benban Solar Plant — Aswan

The site had extremely high and vertically variable soil resistivity, non-achieving grounding values, return-current concerns and tracker-control failures.

Previous testing relied heavily on clamp-on measurements.

why the obvious answer can be misleading

Clamp-on earth testing depends on a closed return loop and cannot replace Fall-of-Potential testing for isolated/open electrodes. Short auxiliary spikes can also be inadequate when the near-surface layer is not representative of deeper geology. The measurement plan therefore had to match the topology and soil model.

02

Why it failed

Clamp-on earth testing depends on a closed return loop and cannot replace Fall-of-Potential testing for isolated/open electrodes.

Short auxiliary spikes can also be inadequate when the near-surface layer is not representative of deeper geology.

The measurement plan therefore had to match the topology and soil model.

03

Follow the engineering

Switch between the field condition and the engineering concept. Trace the path and examine what changes.

Inspect the engineering detail

Solar trackers, geology and the measurement objectiveEngineered approach for PIS-CS-006. Profile soil depth and select electrode arrangements from evidence. Use the test method appropriate to isolated or interconnected topology. Verify tracker bonding and correlate measurements with control behaviour. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 006Solar trackers, geology and the measurement objectiveENGINEERED APPROACHTRACKERARRAY STRUCTURE / TRACKER DRIVE / CONTROL INTERFACESSoil model, test topology and control behaviour are separate checks.1231Profile soil depth and selectelectrode arrangements fromevidence.2Use the test methodappropriate to isolated orinterconnected topology.3Verify tracker bonding andcorrelate measurements withcontrol behaviour.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Case 006 · Engineered approach

100%
Solar trackers, geology and the measurement objectiveEngineered approach for PIS-CS-006. Profile soil depth and select electrode arrangements from evidence. Use the test method appropriate to isolated or interconnected topology. Verify tracker bonding and correlate measurements with control behaviour. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 006Solar trackers, geology and the measurement objectiveENGINEERED APPROACHTRACKERARRAY STRUCTURE / TRACKER DRIVE / CONTROL INTERFACESSoil model, test topology and control behaviour are separate checks.1231Profile soil depth and selectelectrode arrangements fromevidence.2Use the test methodappropriate to isolated orinterconnected topology.3Verify tracker bonding andcorrelate measurements withcontrol behaviour.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved

Scroll to inspect. Numbered details match the notes below the drawing. Conceptual geometry; use the case text for the engineering requirements.

What changes

Separate the problem into soil-resistivity characterization, isolated-electrode/grid resistance, on-grid loop checks, continuity, current-path investigation and control/EMC checks.

Teaching schematic · not to scale© PIS Engineering Academy · All rights reserved
04

Correction & verification

Separate the problem into soil-resistivity characterization, isolated-electrode/grid resistance, on-grid loop checks, continuity, current-path investigation and control/EMC checks.

Use appropriate probe geometry and electrode lengths for the actual geology.

Verification recorded in the case

  • Correlate corrected measurements with network modifications and tracker/control behaviour. Do not attribute all control failure to earthing without evidence.
  • Record as-built topology and connection points.
  • Repeat the measurement or functional test under a defined condition.
  • Confirm continuity and mechanical integrity of the corrected path.
  • Document instrument/setup, environmental condition and test method.
  • Close the NCR/case only when evidence supports the conclusion.
References & project context

References are reproduced from the PIS casebook. Select the governing edition and project acceptance criteria before using them for a design. The diagrams explain the concept, rather than define construction dimensions.

IEC 61557-5; IEC 60364 earthing/bonding principles; project-specific renewable-energy grounding and EMC requirements.

PIS reviewed field handbook · PIS-CS-006

View the original social card
05

The engineering lesson

Choose the test method from the electrical topology and geology — not from the instrument available in the technician’s bag.

Take the lesson into your next design review.

Keep exploring

Connected lessons.

All cases
Read a curve, not one assumed probe positionEngineered approach for PIS-CS-031. Extend and document the test line for the actual grid. Plot multiple probe positions; use the justified curve/slope method. Derive and verify the result without assuming a universal position. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 031Read a curve, not one assumed probe positionENGINEERED APPROACHPCCURVE TESTEARTH TESTEREPCMULTIPLE PROBE POSITIONSIllustrative curve only; derive the method and distances from the actualgrid.1231Extend and document the testline for the actual grid.2Plot multiple probepositions; use the justifiedcurve/slope method.3Derive and verify the resultwithout assuming a universalposition.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
31

Measurement

A large grid cannot be tested like a rod

A large grid cannot be tested like a small rod.

Benban Solar Park3 min
Move auxiliary probes beyond grid influenceEngineered approach for PIS-CS-032. Base separation on grid dimensions and actual site constraints. Extend current and potential probe arrangements appropriately. Validate the curve and repeat direction where site conditions require. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 032Move auxiliary probes beyond grid influenceENGINEERED APPROACHPCCURVE TESTEARTH TESTEREPCVERIFY REMOTE REFERENCEIllustrative curve only; derive the method and distances from the actualgrid.1231Base separation on griddimensions and actual siteconstraints.2Extend current and potentialprobe arrangementsappropriately.3Validate the curve and repeatdirection where siteconditions require.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
32

Measurement

Testing beyond the grid's influence zone

The auxiliary probes were inside the system they were supposed to measure from outside.

Interconnected systems3 min
Survey zone, installed soil and electrode interactionEngineered approach for PIS-CS-001. Characterise the actual soil around the installed electrodes. Coordinate spacing using the site soil model and electrode geometry. Validate probe geometry and repeatability before accepting the reading. Conceptual teaching detail, not an as-built drawing or construction instruction. © PIS Engineering Academy · All rights reserved.PIS ENGINEERING / CASE 001Survey zone, installed soil and electrode interactionENGINEERED APPROACHSURVEYED SOILBACKFILLED INSTALLATIONSOIL SURVEYSOIL RESISTIVITYC1P1P2C2COORDINATED SPACINGSoil changes across the site. Rods interact below ground.1231Characterise the actual soilaround the installedelectrodes.2Coordinate spacing using thesite soil model and electrodegeometry.3Validate probe geometry andrepeatability beforeaccepting the reading.READ THE DETAILEquipment, joints and current-path interfaces are shown in context.Conceptual teaching plate · no project dimensions or acceptance limits impliedPIS / REV 03© PIS Engineering Academy · All rights reserved
01

Measurement

Soil resistivity & rod spacing

Never Trust One Soil Resistivity Test.

New Cairo3 min